1. Safety pre assessment:
(1) Letter of Authorization for Safety Assessment
(2) Copy of business license
(3) Feasibility study report and relevant drawings
(4) Engineering geological survey report
(5) Project establishment documents and filing documents
(6) Project land planning permit document or project site selection proposal
2. Safety acceptance evaluation:
(1) Letter of Authorization for Safety Assessment
(2) Copy of business license
(3) List of main responsible persons and safety production management personnel of the enterprise and copies of qualification certificates
(4) List of special operators and copies of operation certificates
(5) Security management organization setting document
(6) List of Safety Production Rules and Operating Procedures
(7) Work safety responsibility system, emergency plan and filing documents, drill summary
(8) Project approval documents
(9) Safety Pre assessment Report and filing form
(10) Special Safety Chapter and filing approval documents
(11) Preliminary Design Specification and relevant as built drawings
(12) Copies of qualification certificates of design, construction and supervision units
(13) Construction and supervision completion acceptance data (on-site reference, partial copying or borrowing)
(14) Fire detection acceptance report and review comments of fire department
(15) Safety test report of lightning arrester
(16) Special equipment inspection certificate, special equipment use registration certificate
(17) List of main production equipment, special equipment catalogue and list of fire-fighting equipment configuration
(18) Production trial run report (if there is an accident during the trial run, there should be accident handling)
(19) Payment certificate of industrial injury insurance, classification assessment and filing documents of major hazard installations
(20) Completion of safety investment (list description)
(21) Allocation list of labor protection articles
(22) Land use certificate (site selection opinion, land use planning permit or land use certificate, etc.)
(23) Certification materials for withdrawal and use of work safety expenses
(24) Other data (such as the type, quantity and storage mode of the dangerous chemicals involved, the qualification certificate of the supplier of dangerous chemicals, the qualification certificate of the transport unit of dangerous chemicals, etc.)
Preparation of Lanzhou Safety Impact Assessment Report
3. Safety status assessment:
(1) Safety Assessment
(2) Business license of construction unit
(3) Opinions on fire control acceptance of construction engineering
(4) Land planning documents of construction project
(5) Test and inspection report and certificate of special equipment
(6) Detection, inspection report and certificate of lightning and static protection
(7) General layout of the project
(8) Project process introduction
(9) Project equipment list
(10) Project safety management system, emergency plan or emergency plan filing registration form
(11) Certificate of special operation personnel of the project, and relevant certification materials for the enterprise to pay industrial injury insurance for employees
In actual operation, due to the different nature and production content of each project, there are individual differences in the collected data, which shall be subject to the list of data sent by the safety assessment personnel or the on-site collection requirements. Gansu Project Energy Saving Report Writing